Optimus Maximus Development Schedule

Plastic parts tooling will be ready by July 10.

OLED tooling will be ready by July 16.

Early August - fully functional prototype.

Bad news: after the develoopment and before mass production there's 10 weeks of waiting for the sertification procedures - CE, FCC, WEEE, ROHS. Most likely there will be something to be changed to comply with the regulations.



Please note that in Taiwan, just as in Russia, May 1st is a holiday called Labor Day (so no one works).

Production schedule:
November 31, 2007 - 200 keyboards
December 2007 - 200 keyboards
January 2008 - 400 keyboards

Tomorrow I'll open a count-down clock to tick until pre-orders start.

To be or not to be - the price for the Optimus Maximus keyboard with finalized specs is US$ 1564 (Shakespeare's birthday).
Subscribe
  • Post a new comment

    Error

    default userpic

    Your IP address will be recorded 

    When you submit the form an invisible reCAPTCHA check will be performed.
    You must follow the Privacy Policy and Google Terms of use.
  • 56 comments
Previous
← Ctrl ← Alt
Next
Ctrl → Alt →
Previous
← Ctrl ← Alt
Next
Ctrl → Alt →